Jepak–Bintulu Airport dual carriageway project ahead of schedule, completion set for Oct 2027

Jepak–Bintulu Airport dual carriageway project ahead of schedule, completion set for Oct 2027

BINTULU (May 23): Construction of the dual-carriageway linking the Jepak Roundabout to the Bintulu Airport Roundabout is progressing ahead of schedule. According to a project fact sheet released by the Sarawak Public Works Department (JKR), the project had achieved 15.34 per cent physical progress as of April 2026, surpassing the scheduled target of 12.42 per […] The post Jepak–Bintulu Airport dual carriageway project ahead of schedule, completion set for Oct 2027 appeared first on Borneo Post Online .